Please note the following dates:
28th February – temporary removal of the Outdoor Dining Areas in Bellair Street.
21st March – Drainage works between Macaulay Road and Bridges Lane. Estimated 2-week disruption.
4th April – Drainage works between Bridges Road and Wight Street. Estimated 3-week disruption.
4th April – Bluestone kerbing. Estimated 4 weeks.
25th April to mid-June – Footpath Reconstruction including swirls, mosaics, service pits relocations & asphalt. Minimal disruption and contained to immediate work area.
June – reinstatement of Outdoor Dining Areas.